Making good and decoration
Repairs to leaves, frames and surrounding finishes leave marks. If decoration is excluded, you have a second trade and a second cost to arrange after completion.
Cost & Process Guide
If you are holding two or three quotations against the same fire door report and they are thousands of pounds apart, the usual explanation is not that one contractor is cheap. It is that they are quoting different work. This guide shows how to put them on a like-for-like basis before you award anything.
Comparison only means something once every quotation is answering the same question. The quickest way there is to rebuild each one against your own door list rather than reading each contractor's layout on its own terms.
Where a quotation has no door references at all, that in itself is useful information: it cannot be checked, varied or closed out door by door later.
Repairs to leaves, frames and surrounding finishes leave marks. If decoration is excluded, you have a second trade and a second cost to arrange after completion.
A quotation covering only the door leaf can leave an unsound frame or an unsealed perimeter untouched, which undermines the work that was paid for.
Check which items are listed by name. Closers, hinges, latches, seals and signage quietly moving out of scope is a very common source of variation.
Daytime access to occupied dwellings, no-access revisits, out-of-hours working and access equipment are real costs. Cheap quotations often assume the best case.
Per-door records, photographs and a close-out pack are what prevent the same doors being re-surveyed next year. If they are not in scope, you are buying works without evidence.
Components should be suitable for the doorset concerned, with supporting documentation. A cheaper like-for-nothing component is not a saving.
For a single report with a finite list of defects, a priced schedule against door references is normally clearest. For continuing programmes across several buildings, a schedule of rates can be the better instrument: agreed prices for defined items, applied as works arise.
It only works, though, if the item definitions are tight. A rate for “renew closer” means little unless it states the closer type, whether adjustment and commissioning are included, and whether making good is covered.
None of these are trick questions. A contractor who prices this work regularly will answer them without hesitation, and the answers usually explain the price gap entirely.
What the priced items themselves involve.
Send us your report or door list and we will price it per door reference, with repairs and replacements separated and exclusions stated on the face of the quotation.