Resident access
Notice, appointments, missed visits and evening or weekend attendance. On flat entrance programmes this is routinely the largest cost element and the one most often underestimated.
Cost Guide
A block of flats is not one fire door job with a single rate. It is at least two quite different jobs — communal doors and flat entrance doors — with different access, different cost per door and often different people paying. This guide explains how a whole-block budget is put together and where the money actually goes.
The first thing that makes a block budget usable is a split by door type and location, not a single total divided by the number of doors. Average cost per door across a whole block hides the two facts you need most: which doors are expensive to reach, and which are expensive to put right.
Once a schedule is grouped this way, most blocks turn out to have a large number of low-cost communal items, a smaller number of access-driven flat entrance items, and a short list of doors that genuinely need replacing.
Notice, appointments, missed visits and evening or weekend attendance. On flat entrance programmes this is routinely the largest cost element and the one most often underestimated.
Thirty doors in one core price very differently from thirty doors spread across six low-rise blocks on the same estate. Travel and set-up are shared or repeated accordingly.
Where specification and previous works are known, works are specified straight away. Where nothing is recorded, investigation time comes before any component is ordered.
Blocks with successive part-programmes often hold several door types and hardware standards. That variety increases both survey time and the number of component lines.
Decoration, frame repairs and wall finishes around works are real lines in a communal area and are frequently excluded from cheaper quotations.
Per-door records, photographs and a close-out pack take time, and they are what stops the same doors being re-surveyed and re-priced next year.
We do not publish fixed per-door or per-flat prices for blocks, and we do not give indicative figures before we know what is in the building. A number invented over the phone ends up in a service charge estimate or a section 20 consultation, and it will not survive contact with the actual doors.
What we will do is price your schedule per door reference, with communal and flat entrance work separated, provisional items identified as provisional, and the VAT treatment stated on the quotation. If you hold a door-by-door report, we can price directly from it.
Where the schedule exceeds the available budget, price the whole thing once so the full liability is known, then decide the order deliberately.
The works themselves, and the rest of the cost picture.
Send the door-by-door report, FRA action list or a core-by-core door count and we will price the block with communal and flat entrance works separated.